卫生间防水的流程
Waterproof process of toilet
1、刷第一遍防水涂料。
1. Brush the first coat of waterproof paint.
施工前确保工地干净、干燥,防水涂料要涂满,无遗漏,与基层结合牢固,无裂纹、无气泡、无脱落现象。涂刷高度一致,厚度要达到产品规定要求。白钢雕塑 小型滚揉机 防火电缆 托辊设备 水刀切割机 铜钟 石雕狮子 校园不锈钢雕塑 扭王块模具
Before construction, ensure that the construction site is clean and dry, and the waterproof coating shall be fully coated without omission. It shall be firmly combined with the base course without crack, bubble and falling off. The brushing height shall be consistent, and the thickness shall meet the specified requirements of the product.
2、刷第二遍防水涂料。
2. Brush the second coat of waterproof paint.
注意第一、第二遍防水涂料间需要有一定时间间隔,待第一遍涂料干透后才能进行第二遍,具体时间视涂料而定。间隔时间太短,防水的效果会大打折扣。
Note that there shall be a certain time interval between the first and second waterproof coatings. The second coating can be carried out only after the first coating is dry. The specific time depends on the coating. If the interval is too short, the waterproof effect will be greatly reduced.
3、铺保护层。
3. Lay protective layer.
为防止之后的施工破坏防水层,需在防水涂料表面铺上保护层。保护层要完全覆盖防水层,无遗漏,与基层结合牢固,无裂纹,无气泡,无脱落现象。
In order to prevent subsequent construction from damaging the waterproof layer, a protective layer shall be paved on the surface of the waterproof coating. The protective layer shall completely cover the waterproof layer without omission, and shall be firmly combined with the base layer without crack, bubble and falling off.
4、闭水试验。
4. Closed water test.
闭水试验时,地面最高点的水线不能低于2厘米,保存至少24小时,观察无渗漏现象后方算合格。如有渗漏,需重做,切莫不能疏忽大意。
During the closed water test, the water line at the highest point of the ground shall not be less than 2cm, and shall be kept for at least 24 hours. It shall be considered as qualified after no leakage is observed. If there is leakage, it needs to be redone. Don't be careless.